Hakunila major region
Construction of the Vantaa Light Rail Begins on Hakunilantie and Tilustie
Construction will begin during April at three locations. Preparatory works will start in stages on Hakunilantie, Tilustie and on the new street connection, Rivieranraitti. The works will cause temporary changes to traffic arrangements.
Vantaa will become a modern and attractive light rail city
For many Vantaa residents, the light rail will mean smoother mobility in everyday life in the future. But that’s not all – an entire light rail city will be built around the light rail.
Construction of the light rail on Länsimäentie
Follow the progress of light rail construction from Fazerila to Mellunmäki. In the future, the light rail will run along Länsimäentie to the Mellunmäki metro station.
Construction of the Light Rail from Hakunila to Fazerila
Follow the progress of light rail construction in Hakunila, Vaarala and Fazerila.
Vanha Porvoontie will reopen to traffic on 23 February 2026 – changes to traffic arrangements at the intersection of Sammaltie and Kyytitie
The concrete culvert found beneath Vanha Porvoontie has been demolished. A new stormwater line, district heating line and cable ducts have been installed at the roadway. The intersection area will reopen to vehicular traffic on 23 February 2026. Once the intersection is reopened, construction work
Kyytitie between Heidehofintie–Sammaltie/Kanervantie will be closed to vehicle traffic from 2 March 2026 – the closure will last until the end of August 2027
Ground reinforcement works, relocation of municipal utilities, and construction of a new bridge and track for the future tramway will begin on Kyytitie. As a result, Kyytitie will be closed to vehicle traffic between Heidehofintie–Sammaltie/Kanervantie from 2 March 2026. Access to the Neste station
Construction phases causing especially loud noise will begin on Kyytitie in late February and early March
In late February and early March, construction work causing especially loud noise will take place along Kyytitie in the northern part of Porttipuisto and near Heidehof Park.
Invitation to Resident Information Sessions – Construction of the Vantaa Light Rail Begins on Hakunilantie
According to current plans, construction of the Vantaa Light Rail will begin on Hakunilantie in spring 2026. We will organise resident information sessions about the upcoming street construction works: one in Vaarala Chapel (Kirkkokuja 2) on 23 February from 18:00 to 19:00, and another in
Service Disruption Notice! Telecommunications cable damaged on Kyytitie
During construction work on Kyytitie, a telecommunications cable was damaged. This is causing disruptions to internet connectivity in the Kuusikko, Hakkilankallio and Porttipuisto areas. Problems have been reported at least with Elisa’s connections. Repair work is currently underway, and we will
The bridge over Porvoonväylä on Länsimäentie (Västerkullavägen) will become single-lane starting 2 February 2026 – construction work will cause special noise in the area.
Construction of a new bridge over Porvoonväylä will begin at the location of the current bridge. The work will start with the building of temporary support walls, including excavation and sheet piling. These works will cause special noise in the surrounding area. Due to the construction, the bridge