Changes to traffic arrangements on Hakunilantie between Raudikkokuja and Hevoshaantie – temporary bus stops in use
Traffic arrangements on Hakunilantie will change during week 19. Construction work will move to the eastern side of the street, and pedestrian and cycling routes will be partly redirected back to the western side. These arrangements will not affect motor vehicle traffic. The Raudikkopolku bus stops
Rajatie will be closed to motor vehicle traffic starting 11.5.
Motor vehicle traffic on Rajatie will be cut off over a distance of approximately 40 metres east of the Rajapolku intersection in order to prevent through traffic. The closed section of the street will be converted into a route for pedestrians and cyclists.
Work phases causing significant noise will begin on Kyytitie from May 2026
Construction of the Vantaa tramway is progressing, and in May, work phases causing significant noise will begin in new areas along Kyytitie. Noisy work will be carried out on weekdays from 7:00 to 18:00.
Summer season passes will not be sold for Kuusijärvi electric saunas due to renovation
Kuusijärven päärakennuksen sähkösauna- ja pesutilan remontin vuoksi sähkösaunoihin ei myydä kesän kausikorttia kaudelle 1.5.–31.8.
Respond to the survey on tram communication by 12 May
The City of Vantaa wants to hear the experiences of residents in Tikkurila and Hakunila regarding communication about the tram project. The aim is to further improve tram-related communication and ensure that information reaches all residents in the area.
Construction begins on Tilustie and the new tram street connection on Rivieranraitio
Construction work on Tilustie and Rivieranraitio will begin in week 16. As preparatory work, topsoil will be removed and surcharge embankments will be constructed to strengthen the ground. The first phase of construction will not cause any changes to traffic arrangements.
Construction on Hakunilantie begins on the section between Raudikkokuja and Hevoshaantie
On Hakunilantie, changes to traffic arrangements and the delineation of construction areas will begin in week 15. The traffic arrangements concern the west side of the street and will cause changes to pedestrian and cycling routes. Vehicle access will remain unchanged.
Preparatory construction works for the Vantaa tramway to begin in April between Lahdenväylä and Hakunilantie
Preparatory works related to the construction of the Vantaa tramway will begin in early April in the area between Lahdenväylä and Hakunilantie. These works include, among other things, tree felling, removal of stumps and topsoil, preparations for changes in traffic arrangements, and removal of
Blasting works causing significant noise to begin in April on Länsimäentie near the bridge over Porvoonväylä
Blasting works will be carried out on both sides of the bridge over Porvoonväylä on Länsimäentie during April, causing significant noise in the surrounding area. The works are scheduled to begin in early April and are expected to last approximately two months. The works are part of earthworks
Construction works begin on Länsimäentie – traffic, pedestrian and cycling detours in April
The section of Länsimäentie between Rajakentäntie and Keihästie will be closed to traffic on Monday, April 20. The road will be closed during the day, and traffic will be diverted via Pallastunturintie. The arrangements also apply to bus routes that have previously used Länsimäentie. The section