Tag: Vantaa Light Rail Kuninkaala - Mellunmäki
Municipal Infrastructure and Foundations Under Construction at the Vaarala Depot, Pedestrian and Cycling Connections Reopened
Rock excavation and crushing works at the Vaarala depot have been completed, and construction has now progressed to municipal infrastructure and depot structure works. The pedestrian and cycling connection via Lemmenkuja has been reopened following the completion of construction works, and temporary
Changes to traffic arrangements on Hakunilantie at the Hevoshaantie underpass
Rehabilitation works on the western side of the Hevoshaantie underpass have been completed, and construction will now move to the eastern side of the underpass. Traffic arrangements required for the new construction phase will be implemented in week 43, when traffic will be shifted to the western
Fazerintie to be rerouted from 13 October – New temporary bus stop and traffic arrangements to take effect
New temporary traffic and bus stop arrangements will be introduced on Fazerintie on 13 October as earth-cutting works begin along the street section during week 42. As a result, vehicular traffic, pedestrians, and cyclists will be directed to a temporary diversion route around the work site, and
Lemmenkuja Construction Works in the Final Stage, Detour Route Remains in Use Until the End of Week 41
Municipal infrastructure construction works on Lemmenkuja have been completed, but final finishing works will continue during week 41. Due to these works, the pedestrian and cycling connection on Lemmenkuja will remain closed until 9 October 2026.
Bus Stops on Kirkkokuja and Rajatie Relocated in Vaarala from 6.10.
Construction work in Vaarala is progressing. Preparatory works for the construction of the Kuussillantie roundabout will begin, and as a result, new locations for the Kirkkokuja and Rajatie bus stops will be introduced from 6 October.
Change to Traffic Arrangements at the Kyytitie and Hakunilantie Intersection
Traffic arrangements at the intersection of Kyytitie and Hakunilantie will be modified during Week 41. To facilitate the progress of water utility construction works, the work area will be expanded to the southern side of Kyytitie. As a result of the change, vehicle traffic will be directed to pass
Construction of the new fence at Länsimäki dog park begins on Thursday, 1 October 2026 – short closure in the morning
Construction of the new fence at Länsimäki dog park will begin on Thursday, 1 October 2026.
Excavation works completed at Rivieranraitio
A significant milestone will be reached this week in the construction of the future tram street connection at Rivieranraittio, as the excavation works in the area are completed. A few final blasting operations will be carried out during the week, after which the excavated rock will be transported
Traffic arrangements at the intersection of Keihästie and Länsimäentie to change from Monday, 28 September 2026
New traffic arrangements will be introduced at the intersection of Keihästie and Länsimäentie on Monday, 28 September 2026. The changes are part of the previously announced two-week closure of Keihästie.
Construction of the New Bridge over Porvoo Highway Progresses in Länsimäki – Night Work in Weeks 40–41
Construction of the Vantaa light rail is progressing in Länsimäki, along Länsimäentie and in the area surrounding the bridge over Porvoo Highway. Over the coming weeks, changes will be made to traffic arrangements, and structures for the new bridge will be installed at the construction site.